Wednesday 11/5 - Maint replaced Port Fire Panel.
Thursday 12/5 - Maint replaced Genset engine mount.
Friday 13/5 - Vac'ed 15ltrs of water from engine rooms.
Saturday 14/5 - Maint cleaned Genset strainer.
Sunday 15/5 - Completed 3mthly maintenance checks.
Tuesday 17/5 - I wasn't here.
Wednesday 18/ - vessel was treated for cockroaches.
Thursday 19/5 - MRF'ed Stb Fire pump strainer-repaired crack in Strainer is leaking.
Saturday 21/5 - MRF'ed Fire Alarm Panels - wired in back to front.
Sunday 22/5 - completed weekly and monthly maintenance checks
MRF'ed Boarding ramp from GL4 cracked. MRF'ed port side fwd void hatch seal.
Monday 23/5 - Vacced out 8ltrs raw water from Stb bilge. Removed 2kg sopping soaker pads did not replace due to the excess water accumulating in the bilge.
24,25,26 I wasn't here. Ian Fleetwood completed two weekly and monthly maintenance checks, (already done 15/5).
27/5 I wasn't here. - Boarding ramp @ GL4 repaired and returned.
29/5 - MRF'ed Genset telltale low water pressure.
30/5 - completed Weekly Maintenance checks. Maint on board to check Genset water flow and cleaned Genset strainer. Seems better.
Vessel vac'ed and mopped.
31/5 - Lady bins changed out. Seats vacuumed.
The Stb engine room alarm (first alarm) has been repaired or replaced at some point.
Alarm panels have been returned to their correct configuration at some point.
31/5 - Maint on board repaired port fwd hatch seal.
Signed off on all the MRF's that I could see were completed as requested by Gene but most of them didn't close. I emailed Gene suggesting he sign off at his end. You may receive correspondence regarding this.
New spill kit onboard. Bravo Flag is in our Pigeon hole. (I forgot to take it out before I took the old kit up to the office).
All relevant emails flagged.
Have a good swing.