Hi Ian,
Vessel is running fine.
Please check flagged emails.
Lifejacket demo to be done on vessel twice weekly from now on. We did one today Wednesday 26th.
Aft Ramp to be used at GL4 for unloading. We have been putting it across on the 0540 run and also the 0700 run.
Harnesses for roof have been given to Willy for servicing.
2 Chimes are to be used for passengers disembarking at GL4 on the 0540 Run. First Chime for GLNG DSO operators, followed 30 Seconds later by second chime for contractors. See email from Lee Jorgason.
Waiting on 12 Mm braided Black line to replace bowsing lines on port side. One for the forward bowsing line port side is made up and hanging in wheelhouse cupboard, so you only need to make the second Line. Starboard side has been replaced already. Cable tie mounts and cable ties are in wheelhouse draw, and sicaflex in wheelhouse fridge.
Waiting on stores order for chain and clips, to be placed across stern ramp at GL4.
Latest Version of updated Paper Charts onboard. No updates needed.
Keep watch on Fenders with tyres against them at GL4 in case they slip down below vessels Sponson. They have been raised once and are fine but will cause damage to Vynal Wrap if they fall below Sponson.
Please read email regarding chaffed anchor warp. MRF Submitted.
Annemaree ✌️