Torresian Master Hand-Over 2nd August.
Ron, Jas. welcome back to what could be our lat swing
there have been major changes to ourselves as you will be aware by now. Mainly crewing and run times. Schedule onboard
Cap Sunrise is demobilised as of 15-8-17. 2x Master 4 to go ( I believe Des and Dale)
boat at running good although with a few bums on seats, it is running slower
Stbd toilet finally stopped flushing. Locked door to toilet. Apparently maintenance department have new toilet switches on order.
Shaun & Brodie changed both house batteries out for 2 new ones. Shaun said battery charger is not rated to charge both house batteries. Shaun will consult with Jesse about possibly changing the battery charger as well.
Seal needs to be replaced on cam lock connection of sullage hose. Cam lock is lose once connected to outlet on the boat.
Shore power has been tripping out. This is after lots of water over the bow one day , (winds a constant 30 to 35 knots gusting over 40 knots. Heavy rain.) an aces electrician has been down and tested everything, there was a problem in the power board in the wheelhouse. This has been thrown and another in its place. Was all good for nearly a week, then same issue. Upon washing down it tripped again, trial and error by bringing all circuits online one by one, showed the fwd winch for bow ramp circuit was the cause, this has been isolated both locally and by leaving the breaker off. Problem has gone away ( I hope)
all important ant emails have been flagged.
Air Conditioning contractor (Mick) to look at the forward main cabin air conditioning unit. He said it needs to be replaced. Sealink to decide their options.
Replaced rubber Seal on fore deck hatch port side.
Supply requisition ID # 1792 Walled mounted hand towel dispenser (3rd request in 2 months).
Torresian internet box from under the dash and been sent away for repair. The power cable on the dongle is hit and miss but have been getting it to work
Boat Phone charger has a loose connection at the base of the phone. The Phone taking longer to charge.
july 23 start two full weeks of no wash at WICET. For barge 1201 two weeks from July 23 no wash current
july 26 email fron from Dave to see notice to Mariners 333(T) of 2016 regarding Jack p Barge 'Ocean'driller and Shackleton working in vicinity of Clinton main and bypass NO WASH. See notice
vessel is full of fuel, water full and poo empty
have removed large window ledges internally and got rid of the crap