Hi Oli,
boat is running ok,
we had some issues on Saturday with port genset not running and the stbd one shut down because the temps went up when using only that one. Electrician came onboard to have a look at the pt genset and eventually it started running again but they don't know what the issue was. Has worked fine for the last couple of days.
The 2 small liferafts have been sent off for service on the 4th of March and still haven't made it back, the other 2 big ones are due on the 23rd of March and the 1st of April, you'll have to arrange the swap with Nathan when the others get back.
I've changed all 5 hydrostatic releases that were out of date.
Electrical certificate is due on the 23rd of March, I've spoke to Luke about it and he said he's arranging a new system and make that a 4 years certificate, they will start the process of doing all the boat this month, you might want to chase him up to see when they can get this done on our vessel.
We are missing the watch bill, passage & manoeuvring plan Flipchart. They sent an email that we had it in our pigeon hole, but when I went to pick that up it wasn't there. They should get us a new one soon.
See flagged emails. One of them regards EPIRB Registrations, Dave wanted to make everyone aware in the handover report. They don't issue stickers for them anymore, but they gave us copy of the paperwork that states every boat registration on it, it's kept in the SMS certificates.
Plotter has been playing up, now only works on one screen, MRF's are in.
We did yearly checks and checked all lifejackets lights, they all expire in August this year, I've emailed Dave he told me to remind him in June. I've put that up on the board.
Have a good one,
Ale.