Genset 500 hr service completed 11/09/23
new electrical cert 7/09/23 in SMS and cert register
Gateway dredge vessel in service up to 30/09/23 see flagged email
gateway dredging project completed as per notams #812(T) former notice
new forward spring CP1
Dull transmission UHF house radio MRF #9014submitted 19/09/23 new radio ordered
20/09/2023 port main engine starter fault removed and replaced by shore based engineer at CP3 MRF #9021
new radiator cap stbd side 21/09/23 expansion tank now works as it should. Coolant level has been within parameters without need to top it up.
new fender in place at marina 21/09/23
Maintenance installed new E/R fire detector heat sensors and bases. Nil faults recorded
scrubbed down down vessel 25-26/09
soaker pads and E/Rooms cleaned