Hi all,
Welcome back.
two new air conditioning were installed on 02/05/2023 Tuesday. These are the Port mid aft & the Port aft units. The aircon guys will install two more units today Wednesday 03/05/2023, these will be the Port mid fwd & Port fwd units. Management will arrange with Dan to pull into service wharf after morning runs for these two units to be craned onboard, then the Aircon guys will come to our marina berth to install. They also need to check the Port mid fwd unit which is coming up with a fault.
Probably the biggest news is that maintenance replaced the Starboard inner & outer jet bucket cylinders x 2. They floated the fwd voids to lift the starboard stern up to enable access. They did an awesome job.
please check blink or email for information regarding transporting of dangerous goods. I have emailed Willie with questions regarding batteries to ask if this extends to hand held tools in tool bags ect. Look for his reply via email, it hasn't come through yet.
We have ordered a new kettle as the old one was leaking from its base. We have also ordered a new boat hook for the Port Midships, old one falling apart so be aware that there isn't a boat hook there presently.
Aft spring replaced at QC4
Stern line replaced GL3
New batteries for Port main Engine installed & dated 02/05/2023.
thanks
Jodie